Australia & NZ

Pipeline Construction Projects

Find out more about our Pipeline Construction services

Customer Project Location Scope Dates
Senex Energy Snatcher to Charo Oil Flow Line Cooper Basin, SA Supply and install 5km Flexpipe HT Linepipe
Fabricate and install export oil pump and electrical auxillary skids
September - October 2012
Santos Ltd / Aurecon Above Ground FlexPipe Water Line Cooper Basin, SA Supply and install 17 km Flexpipe Linepipe and Flexpipe HT Linepipe above ground for temporary water line November 2012
Santos Ltd FlexPipe Oil Flow Line Cooper Basin, SA Supply and install 171km FlexPipe Linepipe and FlexPipe HT Linepipe
Install 171km fibre optic cable
August 2012 – January 2013
QGC Domestic Gathering Works Bellevue Field Chinchilla, QLD Install 22km HDPE gas and water lines
Mulch 10km RoW
June – October 2011
QGC Domestic Gathering Works Bellevue Field Extension Chinchilla, QLD Install 60km HDPE gas and water lines
Mulch 41km RoW
November - December 2011
Santos Ltd Moomba HT Flexpipe Pilot Project Moomba, SA Install 7km 3” high temperature FlexPipe HT Linepipe - Australian-first installation March 2011
Eastern Star Gas Bibblewindi Pilot Project Narrabri NSW Install 3.5km 125m HDPE
Mulch 1.75km  ROW
March – April 2011

Fabrication Projects

Find out more about our Fabrication services

Customer Project Location Scope Dates
Senex Energy Snatcher Facility Fabrication Murarrie QLD Fabricate Export Oil Pump skid
Fabricate Electrical Auxiliary skid  
September – November 2012

Civil Works Projects

Find out more about our Civil Infrastructure services

Customer Project Location Scope Dates
Eastern Star Gas / Santos Ltd Water Treatment Plant Maintenance Narrabri, NSW Water treatment plant upgrade & associated pipelines June 2011 – August 2012

Mining Services Projects

Find out more about our Mining Infrastructure services

Customer Project Location Scope Dates
BHP Mitsubishi Alliance Riverside Exploration Site Rehabilitation Works Bowen Basin, QLD Preparation of Sumps, Access Tracks and Drill Pads
Operations Support
Rehabilitation of Drill Pad Sites
Supply of quarried material
July 2010 – May 2011
Cardno Caval Ridge Mine Site Rehabilitation Works Bowen Basin, QLD Preparation of Sumps, Access Tracks and Drill Pads
Operations Support
Rehabilitation of Drill Pad Sites
September 2010 - July 2011
BHP Mitsubishi Alliance Goonyella Riverside Mine Site Rehabilitation Works Bowen Basin, QLD Preparation of Sumps, Access Tracks and Drill Pads
Operations Support
Rehabilitation of Drill Pad Sites
November 2010 – July 2011
Thiess TAMS Riverside Mine Site Rehabilitation Works Bowen Basin, QLD Preparation of Sumps, Access Tracks and Drill Pads
Operations Support
Rehabilitation of Drill Pad Sites
January – August 2011
Thiess Southwalker Mine Site Rehabilitation Works Bowen Basin, QLD Preparation of Sumps, Access Tracks and Drill Pads
Operations Support
Rehabilitation of Drill Pad Sites
March – August 2011
BHP Mitsubishi Alliance Peak Downs Exploration Site Rehabilitation Works Bowen Basin, QLD Preparation of Sumps, Access Tracks and Drill Pads
Operations Support
Rehabilitation of Drill Pad Sites
April - June 2011
Thiess Poitrel TAMS Mine Site Rehabilitation Works Bowen Basin, QLD Preparation of Sumps, Access Tracks and Drill Pads
Operations Support
Rehabilitation of Drill Pad Sites
May 2011
BHP Mitsubishi Alliance Caval Ridge Bulk Earthworks Bowen Basin, QLD Preparation of Sumps, Access Tracks and Drill Pads
Operations Support
Rehabilitation of Drill Pad Sites
June 2011

Mulching Projects

Visit www.leanfm.com.au to find out more about Lean Field Mulching's capabilities and specialist mulching machinery

Customer Project Location Scope Dates
Geokinetics QGC Pangea Werona Seismic Line Surat Basin, QLD Clear 130km source line February 2012 - ongoing
Vegetation Control Australia PowerLink Powerline Corridor Miles, QLD Mulch 40ha powerline corridor September – November 2012
SEQ Electrical Darwin Robertson Barracks (John Holland) Darwin, NT Mulch 5km x 3m perimeter fence line June 2012
QGC Domestic Gathering Works Bellevue Field Chinchilla, QLD  Mulch 10km RoW June 2011
QGC Domestic Gathering Works Bellevue Field Extension Chinchilla, QLD  Mulch 41km RoW November 2011
QGC Domestic Gathering Works Bellevue Field Extension Chinchilla, QLD  Mulch 41km RoW November 2011

 

Consulting 

 

Customer Project Location Scope Dates
Tasmanian Irrigation Derwent River Feasibility TAS Feasibility study for ploughing HDPE pipelines across the Bridgewater Causeway May 2012