Back to Projects
Australia & NZ
Pipeline Construction Projects
Find out more about our Pipeline Construction services
|
Customer |
Project |
Location |
Scope |
Dates |
|
Senex Energy |
Snatcher to Charo Oil Flow Line |
Cooper Basin, SA |
Supply and install 5km Flexpipe HT Linepipe
Fabricate and install export oil pump and electrical auxillary skids |
September - October 2012 |
|
Santos Ltd / Aurecon |
Above Ground FlexPipe Water Line |
Cooper Basin, SA |
Supply and install 17 km Flexpipe Linepipe and Flexpipe HT Linepipe above ground for temporary water line |
November 2012 |
|
Santos Ltd |
FlexPipe Oil Flow Line |
Cooper Basin, SA |
Supply and install 171km FlexPipe Linepipe and FlexPipe HT Linepipe
Install 171km fibre optic cable |
August 2012 – January 2013 |
|
QGC |
Domestic Gathering Works Bellevue Field |
Chinchilla, QLD |
Install 22km HDPE gas and water lines
Mulch 10km RoW |
June – October 2011 |
|
QGC |
Domestic Gathering Works Bellevue Field Extension |
Chinchilla, QLD |
Install 60km HDPE gas and water lines
Mulch 41km RoW |
November - December 2011 |
|
Santos Ltd |
Moomba HT Flexpipe Pilot Project |
Moomba, SA |
Install 7km 3” high temperature FlexPipe HT Linepipe - Australian-first installation |
March 2011 |
|
Eastern Star Gas |
Bibblewindi Pilot Project |
Narrabri NSW |
Install 3.5km 125m HDPE
Mulch 1.75km ROW |
March – April 2011 |
Fabrication Projects
Find out more about our Fabrication services
|
Customer |
Project |
Location |
Scope |
Dates |
|
Senex Energy |
Snatcher Facility Fabrication |
Murarrie QLD |
Fabricate Export Oil Pump skid
Fabricate Electrical Auxiliary skid |
September – November 2012 |
Civil Works Projects
Find out more about our Civil Infrastructure services
|
Customer |
Project |
Location |
Scope |
Dates |
|
Eastern Star Gas / Santos Ltd |
Water Treatment Plant Maintenance |
Narrabri, NSW |
Water treatment plant upgrade & associated pipelines |
June 2011 – August 2012 |
Mining Services Projects
Find out more about our Mining Infrastructure services
|
Customer |
Project |
Location |
Scope |
Dates |
|
BHP Mitsubishi Alliance |
Riverside Exploration Site Rehabilitation Works |
Bowen Basin, QLD |
Preparation of Sumps, Access Tracks and Drill Pads
Operations Support
Rehabilitation of Drill Pad Sites
Supply of quarried material |
July 2010 – May 2011 |
|
Cardno |
Caval Ridge Mine Site Rehabilitation Works |
Bowen Basin, QLD |
Preparation of Sumps, Access Tracks and Drill Pads
Operations Support
Rehabilitation of Drill Pad Sites |
September 2010 - July 2011 |
|
BHP Mitsubishi Alliance |
Goonyella Riverside Mine Site Rehabilitation Works |
Bowen Basin, QLD |
Preparation of Sumps, Access Tracks and Drill Pads
Operations Support
Rehabilitation of Drill Pad Sites |
November 2010 – July 2011 |
|
Thiess |
TAMS Riverside Mine Site Rehabilitation Works |
Bowen Basin, QLD |
Preparation of Sumps, Access Tracks and Drill Pads
Operations Support
Rehabilitation of Drill Pad Sites |
January – August 2011 |
|
Thiess |
Southwalker Mine Site Rehabilitation Works |
Bowen Basin, QLD |
Preparation of Sumps, Access Tracks and Drill Pads
Operations Support
Rehabilitation of Drill Pad Sites |
March – August 2011 |
|
BHP Mitsubishi Alliance |
Peak Downs Exploration Site Rehabilitation Works |
Bowen Basin, QLD |
Preparation of Sumps, Access Tracks and Drill Pads
Operations Support
Rehabilitation of Drill Pad Sites |
April - June 2011 |
|
Thiess |
Poitrel TAMS Mine Site Rehabilitation Works |
Bowen Basin, QLD |
Preparation of Sumps, Access Tracks and Drill Pads
Operations Support
Rehabilitation of Drill Pad Sites |
May 2011 |
|
BHP Mitsubishi Alliance |
Caval Ridge Bulk Earthworks |
Bowen Basin, QLD |
Preparation of Sumps, Access Tracks and Drill Pads
Operations Support
Rehabilitation of Drill Pad Sites |
June 2011 |
Mulching Projects
Visit www.leanfm.com.au to find out more about Lean Field Mulching's capabilities and specialist mulching machinery
|
Customer |
Project |
Location |
Scope |
Dates |
|
Geokinetics |
QGC Pangea Werona Seismic Line |
Surat Basin, QLD |
Clear 130km source line |
February 2012 - ongoing |
|
Vegetation Control Australia |
PowerLink Powerline Corridor |
Miles, QLD |
Mulch 40ha powerline corridor |
September – November 2012 |
|
SEQ Electrical |
Darwin Robertson Barracks (John Holland) |
Darwin, NT |
Mulch 5km x 3m perimeter fence line |
June 2012 |
|
QGC |
Domestic Gathering Works Bellevue Field |
Chinchilla, QLD |
Mulch 10km RoW |
June 2011 |
|
QGC |
Domestic Gathering Works Bellevue Field Extension |
Chinchilla, QLD |
Mulch 41km RoW |
November 2011 |
|
QGC |
Domestic Gathering Works Bellevue Field Extension |
Chinchilla, QLD |
Mulch 41km RoW |
November 2011 |
Consulting
|
Customer |
Project |
Location |
Scope |
Dates |
|
Tasmanian Irrigation |
Derwent River Feasibility |
TAS |
Feasibility study for ploughing HDPE pipelines across the Bridgewater Causeway |
May 2012 |